ROYALE
ENERGY, INC. ANNOUNCES NEW NATURAL GAS PRODUCTION
San Diego, California, May 17, 1996 -- Royale Energy, Inc. announced
at its Annual Shareholders Meeting in San Diego today that they
are putting two natural gas wells into production. The West
Grimes and Dozier were drilled and completed earlier this year.
The West Grimes was completed in six feet of the lowermost productive
sand with a flow rate of 2,500,000 cubic ft. per day.
Approximately 25 ft. of gas-filled sands in three additional zones
remain behind pipe. Another West Grimes well is scheduled
to be drilled in July. The Dozier well was completed in a
section of the Anderson sands at 6,300 ft. with a flow rate of 3,253,000
cubic feet per day.
The Company has also concluded drilling of its Airport prospect.
The Airport well encountered 26 ft. of gas-filled sands in four
productive pay zones. At this time only the lower Winters
formation was tested. The top four feet of a ten foot thick
Winter sand was perforated and tested at 1,700,000 cubic feet per
day.
Surface facilities have been ordered and the pipeline is being
constructed. The well should be in full production in mid-June.
|